Municipal crews work way slower than a private contractor, and there's a few real reasons for it beyond just salaried guys milking the clock. I've been on a city crew for a while now and the pace difference is real, but it's not usually laziness.
The big one is the schedule. Your street is one stop on a long route, and the crew is probaly bouncing between multiple blocks in the neighborhood. So day one they demo your street, then haul the broken slabs off to the dump or a stockpile, and the pour might happen days later because the truck schedule and the batch plant have to line up. Municipal concrete usually comes from the city's own plant or a contracted supplier with set delivery windows, not a same-morning call like your neighbor's driveway guy made.
Cure time does matter too, but not as much as people think. They can backfill and pull forms the next day in most cases. What actually holds things up is the cleanup and restore phase being a seperate task. The forms stay staked because pulling them and hauling them back to the yard is its own job, and the dirt piles are probably backfill material sitting there waiting for the crew to come grade it out and seed or mulch it. On a private driveway job, one contractor does everything in a tight sequence because he wants his equipment back and his next check. On city work, the same crew might be splitting time between your street and two other blocks. Also, and this is the honest part, there is some padding built in. City jobs often have buffer days for weather, equipment breakdowns, or a water main break that pulls the crew off your street entirely. If they finish early, they don't get to go home, they get assigned to the next thing. So nobody's in a hurry. It's not malicious, it's just that the incentive structure is completly different from a private contractor who eats the cost of every extra day. If the finish looks good and the control joints are cut clean, you're fine. Give it another few days to a week and you'll probably come home to graded dirt and no forms. If the piles are still sitting there in two weeks, that's when a call to public works is worth making.