Neighbour had some LED striplights wired up by a friend.
- Flex joined in 'choc block' terminal strip wrapped with gaffer tape and nailed or screwed to the ceiling.
- Tinned ends of striplight wires not removed before using screw terminals.
- 0.5mm flex, over 3m in length total. The fitted tails to the actual striplights would be even thinner.
- 13 amp fuse in plug.
Redid the job with 'choc box' covers screwed to the ceiling, all flexes cord gripped, 3A fuse in plug.
Not a great job but for a couple of quid better than it was.
I am assuming that each of the points above would constitute a PAT fail.
Interesting point is that the person who wired it all up originally was a health and safety person at a major petrochemical site and had a PAT certificate as part of his job.
I know those courses don't require much in the way of prior electrical knowledge but if you've done a course on electrical safety and are still wrapping terminal strip in tape to join flexes you probably shouldn't be involved in the safety of hundreds of people in industry.