Honestly this reads like a pretty normal day on campus work to me. I've done a few university reno jobs and there was always something like this baked into the job from day one, quiet hours, restricted zones, exams, and in your case an animal that apparently hates hammer…

Read the full reply

So we're doing some reno work at a university and right now the whole jobsite is on standby. Reason? Our hammer drilling was upsetting an orangutan they're running experiments on. That's it. That's the holdup. Me and one other guy are sitting in the truck getting paid $160 an hour to basicly watch the day go by. Meanwhile the GC is off arguing about the whole thing, and from what I can tell there's at least 4 other trades standing around too, so figure 20-30 workers total just waiting on a monkey's opinon of our noise. What is life honestly. Genuine question for you all though. Situations like this where somthing totally outside anyone's control idles an entire site, should the GC eat that or should it get passed down? And is it even worth pushing to reschedule the loud work instead of burning hours sitting around? Curious how you'd play it if you were the one holding the invoice.


Honestly this reads like a pretty normal day on campus work to me. I've done a few university reno jobs and there was always something like this baked into the job from day one, quiet hours, restricted zones, exams, and in your case an animal that apparently hates hammer drills. Anybody who's held the invoice on a campus knows the schedule is never fully yours. That's just the trade you're in when the building belongs to a school.

On who eats it, my take is the GC carries it. It's a standstill nobody in the field caused, and if the GC tries to pass idle hours down to the trades over something like this, good luck keeping subs on the next campus job. I'd document the standby time anyway, keep the crew's hours clean and defensible, and let the GC sort out the rest with the university.

On rescheduling versus burning hours, I'd lean toward pushing for moving the loud work if it's going to be a repeated thing, because sitting around gets old fast even when the pay is good. But if it turns out to be a one-off day, take the paid wait. And honestly, being paid that rate to sit in a truck with a buddy beats swinging a hammer in the cold, so I wouldn't complain too loud.

I'd push back on the idea that the GC should just eat this one. Sitting around getting paid is nice for the guys in the truck, but if I'm the one holding the invoice, that money comes from somewhere, and it shouldn't be me absorbing it because an orangutan two walls over hates hammer drills. That's a change order situation, plain and simple. Document the standby hours, who was idle, and let the GC fight it out with the university over who pays for the delay. That's literally what the GC is off arguing about right now, and honestly that's the right fight to have. On rescheduling, I'd rather see the loud work moved than burn hours. If the drilling can happen in a window when the animal isn't being worked with, everybody wins. The trades get productive days, the university keeps its research running, and nobody's invoicing dead time. Whether that's possible depends on the university's schedule, but it costs nothing to ask. One thing I'd say to you directly: keep your own notes on the idle time. If this drags on and the GC tries to push the standby hours down to the subs later, your paper trail is what protects your crew. I got burned once early on trusting that the paperwork would sort itself out, never again.

Not gonna lie I had to read that twice, a whole site stopped because a lab animal didn't like the noise is wild to me. I only ever done small stuff around my own place so this is way out of my league, but that money just sitting there for everyone while the boss argues sounds like a lot. Question for you, when you say reschedule the loud work, does that mean moving it to a different day or just doing the noisy part somewhere else in the building while the animal is elsewhere? Cause if the second one is an option that seems like the easy fix everyone's ignoring.

The point that hits home for me is that someone at the top should've known about this before mobilizing. I did a small job inside a school building once and every restriction was laid out in the pre-job talk, which rooms were off limits, when we couldn't make noise, all of it. If the university knew there was a lab animal on site, that should've been flagged the same way. That's where my frustration whould go, honestly, not at the orangutan. Was this a total surprise to your crew or was it buried in some paperwork nobody read?

Update: still sitting in the truck, so plenty of time to read the replies. The point about the pre-job talk stuck with me. If restrictions like this were laid out at the start, the GC had to know. So my question is, how do you actually get that in writing? Is it part of the bid documents or something you ask for separately before mobilizing?