Hi.
Original CU has 2.5m long meter tails back to the meter cupboard. I would like to move the CU to a new location, which would result in 5m long meter tails from meter cupboard.
the new meter tails would use the existing cable route but extend further along the wall to the new CU location.
Now I know I need a switch fuse due to new meter tails being over 3m long.
Now my question is this, can the Switch fuse go in the location of the original CU and meet the regs with respect to the new CU's location?
Or has the new switch fuse be moved closer to the meter cupboard?
On a related note, is there any such thing as a fush mounting switch fuse that I can sink into the wall instead of a surface mounted switch fuse?
Regards,
Stephen.