Spent the day laying curb with one of those curb-extruding slipform machines and it was honestly a good time. The curb gets formed right in place, straight over a line of steel rebar cage we set beforehand, so the concrete just wraps right around the steel as it comes out. Watching the shaped concrete emerge behind the mold never gets old. You set the machine on the line, feed it, and it just pulls itself along extruding curb the whole way. The crew in the hi-vis standing nearby keeps an eye on the feed and the finish as it comes off. Ahead of the machine you can see the exposed rebar cage sitting on the prepared surface, waiting for its turn to get encased. Kind of satisfying seeing the whole thing go from bare steel to solid curb in one pass.
Got to run the curb machine today
Nov 20, 2026
Last reply: 2 days ago
3 Replies
Follow replies to this discussion?
Information here may be outdated?
I got to spend a day on a crew running one of these a few summers back and your post brought it right back. The way the machine just crawls along the line and the shaped curb comes out behind it, still soft and clean, is one of the best parts of the job. I never got tired of watching it either.
The thing that stuck with me was the steel. That rebar cage ahead of the machine looks like overkill for a kerb, but once you see the concrete wrap around it in one pass you get why they do it. It's more reinforcement than most people would ever guess goes into something like this. One thing I'd flag for anyone thinking about hiring it done: these slipform machines are only for new work. They lay curb where there wasn't any before, so if you've got a busted-up existing curb you want replaced, this isn't the route. That's a tear-out and pour job, diferent animal entirely.
The folks in hi-vis minding the feed are doing real work too. It looks effortless from the side but somebody has to keep an eye on that concrete going in and the finish coming off, or a good run goes sideways fast.
Funny how different two roads to the same curb can be. Everything I've ever formed was the slow way, wooden forms staked and braced, concrete placed by wheelbarrow and worked by hand with a trowel until my shoulders gave out. Reading your description of the machine just pulling itself along the line while the shape comes out behind it makes my old method look like building a sandcastle with a spoon. The part I keep thinking about is that rebar cage sitting out in front waiting its turn. When I did my own curb along the driveway edge, the steel went in a section at a time and got buried as I poured, so I never really got to see it all laid bare like that in one continuous line.
One thing I'd be curious about, since I've never been near a slipform machine in person: how do you handle a curve or a tight corner with one of those? With forms I'd just bend the boards and deal with the ugly joints afterward. Does the machine track the line itself or does the operator steer it the whole way?
Either way, I get the satisfaction part. There's something about concrete going from loose and grey to a clean defined shape that never stops being rewarding, no matter how you get there.
The thing I keep coming back to from your post is the bare steel sitting there ahead of the machine, just waiting its turn. When I've got a straight run of anything to do I always fuss over the layout for ages, and here the cage is laid out and the machine basically eats it in one go. Does the crew have to keep feeding it continuously once it starts, or can they stop mid run and pick back up without a weak spot in the curb? Always wondered how that works with extruded stuff.
Join the Discussion
Have something to add? Share your thoughts — no account required.
Didn't find your answer?
Ask the community — no account required