Rico needs it, as he says L/360 isn't stiff enough. :-) Based on the discussion I see it as a small definite improvement, when the time comes next week I'll figure out if it is worth the small definite extra work.
Yes, that's a good thing, as the old growth DF is #2 or #3, while the new members will be SS, so we can call it a wash. :-) Actually it's not really a wash, as a few of the old joists have large knots on the bottom half near midspan, that's really bad.
Assuming the old and new have the same E = 1.9 Mpsi and a 20psf live load and 10psf dead load, the old 2x6s spanned 13'9" (good for 14'4" at L/360 deflection) and the old 2x4s spanned 9' (good for 9'1" at L/360). The new 2x8s will span 16'5" (good for 17'2" at L/360). Everything is deflection controlled. So the new 2x8s will be just about as stiff as the old construction.
Good point.
Cheers, Wayne