All, I am working on adding two garages on my property. The larger is a
24X32 and the smaller one is 14X20. My father was in construction and I have done about everything in-home construction, except, major concrete. I have done sidewalks, patios, etc but nothing major. This is where my questions originate.I have read a few books and gotten my permits. I marked out the location of the new garages and squared them up over last week after work. Then last weekend, I broke ground with an excavator and a large bobcat. Knowing that I would be better off (concrete savings) having a professional dig the actual footer, I hired a friend of a friend to dig my footer and I operated the bobcat. Things went as expected and my figures for stone and supplies came out. I am preparing for inspection and this morning I cleared out the roots from a few trees that sit in the back 30 feet of my property. I am planning on pouring the footer then the finished slab.
The one thing that I am concerned about is during the excavation we ran into two leach fields (at 3 feet down), an old septic leach bed and a leach bed from an old gray water system (at 2 feet down). I am positive that these systems are both no longer used and the main tanks are filled with sand. I know this for certain because I did this and the new sewer line to the house (120 feet)with my dad when the city sewer came to our area about 10 years ago. The septic system was original with the house (50 years old) and was about 200 gallons (very very small) and the leach field was only 120 feet in a Y. The gray water system ran the washing machine and dishwasher only and was 110 gallons and had only a 45 feet leach system but had a very large diameter.
How is something like this normally handled?
I have, so far, crushed and removed them from the footer entirely and have filled them with foam and packed the ends with dirt and stone tightly. There was no water in either system as expected.
Are these pipes even a concern at this point?
My next question is concerning the next steps in the concrete process.
My plans, and please correct me if I am wrong, is the following;
1) I will get approval from the city that my footer and stone etc is good. I assume they are mostly concerned with depth, width, and straightness of the footer and the stone is 4 inch or better. 2) I will rebar the footer 3) I will bring in the concrete and pour the footer to the bottom of the stone. (stone started 4 inches below earth grade) 4) I will then place my forms (2X8s) and make sure everything is of correct size and square up the forms. 5) I will place my 6X6 10 Gauge wire mesh to the footer 6) I will then have the concrete brought in and will pour and level out with a Bull float/screeds/maybe even a power trowel. 7) I will then place the garage bolts for the sill board 8) Spray on curing agentNow, I am considering having the above done after I get approval from the city inspection. As I have a friend who has a friend that does this for a living. I have seen his work and I think it looks decent. So everyone knows, this is very against my grain as I hire very few things out. My main concern is the man power behind this and the skill to do the final level/finish but I know getting to this point is a very big step.
Now what should I expect to pay outside the cost of materials to have him do this? What is the norm? I have been told he will bring in 4 guys at $250 a day for the actual pour. What should form, rebar and mesh placement cost me?
I have another option to finish this concrete which is decent as well. I personally have a long time friend that is in the heavy machine operating trade (40 + years) and has done a lot of large scale concrete/masonry in his life. I have seen his work and it is decent.
Any opinions or suggestions?
Sorry for the rambling.
Thanks, Chris Solomon_Man