Well, the slab is laid (75% done Saturday and the last 25% on Sunday).
Hired a Belle Premier 100XT diesel mixer.
6 tons of loose ballast, 40 bags of cement (4 bags spare).After measuring a 5:1 mix using buckets and estimating shovel loads we settled on 22 shovels of ballast and one 25kg bag of cement per load. This worked out at six mixer loads per ton (nominally a 110 litre mixer but this works out at 167 litres; we could have pushed it and mixed a little more but it was easiest working at one bag of cement per mix). Barrow rated at 88 litres and two almost full loads so we were somewhere near. However I can't help thinking that we were nearer 140 - 150 litres and the ballast was slightly under six tons. Whatever.
The six tons of loose ballast used 36 bags of cement so (all things being equal) we were working at the suggested six bags per ton.
There wasn't enough ballast.
Went to B&Q Warehouse on Sunday with the trailer and got a 'ton' bag of ballast and another couple of bags of cement.
With this extra we just scraped home - ended up about a pint short and scraped all the residue out of the mixer :-) We didn't get six full mixes out of the bag so reckon there was less than a ton in there - but nobody knew more than that the bag was rated at 1 ton. Getting anything out of the builders yard end of B&Q warehouse is a farce. It took three people over half an hour to organise a fork lift and get the bag onto the trailer. Five minute job at Jewson. However, B&Q is open on Sundays.
So:
assuming my estimate of volume (3.5 cubic metres) was approximately right the quarry companies who work on 1.5 tons per cubic metre are under estimating. 2 tons per cubic metre would be closer to the mark.
The contenders were (checking back)
Ballast comapnies - 5.25 tons Paving Expert - 6.65 tons or 6.3 tons using McCormack's C20 estimator 'practicaldiy' - 7.77 tons
Estimated actual about 6.9 tons. Could be less if the 'six tons' loose was slightly under and the B&Q bag was slightly under. In which case Paving Expert was about spot on.
Thanks to all for the help.
Pictures to be updated on photo bucket shortly.
Slab is now covered in hessian (to give it a string vest) and a layer of plastic.
Saturday was glorious and sunny. Sunday was damp and miserable. Monday is cold, temperature is below 2C, and it is snowing a little.
I am still not at all sure how much I have laid; thinking back one sure way to know would be to fill the site up with water (inside the damp proof liner) measuring the water on the way in then pumping it out again. Life is, however, too short.
Now to start planning the construction of the shed, and waiting for the weather to warm up enough for block laying.
Cheers
Dave R
Oh, and the valve for the tyre on the builder's barrow packed up over night Saturday. Fortunately I had a second barrow (not quite the same shape as a builder's barrow but it was adequate).