concrete floor installation

another cellar question... as the underslab is solid, firm and dry clay, do you think I'll need to dig it out and add a couple of inches of hardcore or could I just blind it with a thin layer of sand to level it off/protect the DPM ?

LJ

Reply to
in2minds
Loading thread data ...

I'd lay hardcore and concrete first, then DPM then insulate and screed.

Dig ou as far as is necessary to do a proper job.

i.e. about 4" of conctete and hardcore, 2" of polystyrene and 3" of screed.

Reply to
The Natural Philosopher

I'm not screeding the floor, the concrete will be finished floor level

I have/am, just wanted some input before I call the BCO out again

3" of screed ? a little on the excessive side aint it ?

LJ

Reply to
in2minds

Not over insualation, if you don't want cracking...

Reply to
The Natural Philosopher