Hi,
I'll try and keep this brief as it's a very long story.
We own a small plot of land which we purchased with outline permission in place for two dwellings.
It was agreed by all who saw the land that it could easily be pushed to three dwellings, so we decided to apply for three using the normal channels (full plans submission).
The local planning officers looked at the site and recommended that we should be allowed to have three, but a small band of local residents were against the project and contacted thier local Politicians, for this reason the final decision at a local level had to go to a full planning meeting, at which a majority of local councillors said no, because of frankly ludicrous reasons - but a no is a no!
We were therefore forced to go to appeal (written representation). Almost seven months later and error after error on the part of the Inspectorate we have today had a yes - yippppeeee.
Note that the target time for a decision is normally 16 weeks!!!
Our company has suffered financially of the back of these events, namely - having cash tied up, extra fees involved, time spent writing letters etc. etc. etc.
The Architect tells me that compensation may be available.
My questions are: Is this the case? has anyone had any experience? What costs are involved? What are the chances of success? Bear in mind we work mainly within that area are we going to cut our nose off to spight our face when it comes to future decisions?
I thought I'd ask these question here before getting too involved and possibly wasting more time on a 'losing horse'.
Many thanks Chris