Hello,
I'm after some advice please...
The background is a small extension under contract with a local builder, using the srvices of an architect. The build started in May 2003, and was due to finsh July, but actually completed end August 2003.
So far I do not have building regulations approval - the staircase did not have sufficient headroom. I withheld payment of last amount, in part because of the work required to fix the stairs and also as several items in the last valuation were incorrect - e.g it included money I had withheld for 4 weeks damages due to late finishing.
We have now reached an agreement on the work to the stairs that the builder and building regs were happy with - and the works were due to start according to the builder once we had a final snagging list (this had not progressed from August as we were withholding payment, the builder refused to do the snagging).
Since that agreement, the builder then tried to complete just the stair work suggesting he could work on the Good Friday. We delcined as we were away for the weekend, and as the final snagging list had not been sent through. Our architect sent the final snagging list through and requested 7 days notice from them for when the work would start, and confirmation of the agreement that the snagging and stair work would be completed at the same time.
Since then the builder of my extension has invoked the adjudication clause in our contract (JCT).
I offered a final settlement of £4.5K. This was the £9.5K that the last valuation was for, less £2K for damages for late completion, and another £3K reduction was made up of approx £1,500 for not completing the snagging in any way (i.e he only had to fix the stairs) and about £900 in respect of anauthorised variations and an agreement with the buillder to not charge £640 for loft work that was excluded from the contract originally.
The builder has not accepted this - though he not ackowledged it either.
In the adjudication information they sent to RIBA, they state that the amount owing is £7,500 (including retention) - so it looks like they are accepting my claim for £2K damages for late completion.
I am not entirely clear on the builders reason for adjudication - he has yet to agree to complete the snagging list, and nor has he provided pricing for the variations that he carried out.
My architect says he cannot see why the builder would go to adjudication for £3K when the build has not yet gained building regulations approval - but, equally he has never had a contract go to Adjudication.
The appointed adjudicator has now been in touch and advised his fees are £100 / hr and his mileage rate is 55p / mile - and that he needs a site visit with my architect present. He is in West Yorkshhire - I am in North Yorkshire.
My questions are based around how the charges that the adjudicator incurs are proprtioned. I can see that the fees will quickly rack up and be more than the amount I have at dispute with the builder.
Now that the adjudicator has been nominated, should I not approach the builder - my architect is on holiday for a week. Also can we still reach a settlement or do I have to allow the adjudication process to run it's course now ?
Also - any thoughts on my case given the above brief one sided view of things ?
Many thanks. Nick