What do I do with this huge open space between my ceilings and the floor above?

Oct 24, 2026 Last reply: 8 hours ago 4 Replies
Saved reading

First reply

Jake_Ember

Blown-in cellulose actually does fill a tall cavity like that, as long as the crew dense-packs it rather than just letting loose fill drop in. I had basicly the same setup in my old house, a couple feet of open space over the living room ceiling, and the crew ran a hose up thru…

Read the full reply

So I pulled down a ceiling light in our back bedroom to swap it out and poked my head up into the hole, and turns out there's a massive open cavity up there. It runs the whole width of the room, looks like at least a couple feet tall between the ceiling drywall and the floor of the room above. No insulation anywhere, just dusty joist bays and an old plumbing pipe running through. I'm guessing that's why that bedroom and the room above it are always the coldest spots in the house once winter hits. The rest of the place holds heat fine but those two rooms never catch up.



My question is what's the right move here. Can a blown-in insulation crew fill a space that big through a few holes, or does it just slump to the bottom of the cavity and leave the top empty? Would it make more sense to air seal the gaps first and then blow, or does it even matter in a space that tall? And is there any chance this was done on purpose for airflow or some old-school reason I shouldn't mess with? I'd rather figure out the plan before I start cutting more holes in my ceiling than I need to.


Blown-in cellulose actually does fill a tall cavity like that, as long as the crew dense-packs it rather than just letting loose fill drop in. I had basicly the same setup in my old house, a couple feet of open space over the living room ceiling, and the crew ran a hose up thru the light hole and filled bays untill they hit the right pressure. Regular loose blown insulation will settle over time and leave the top few inches empty, so if you go that route, tell them you want it dense-packed, not just fluffed in.

I find it hard to beleive that just blowing material until the crew hits a certain pressure will completley solve the issue, especally given the size of the cavity. Even if they are using a dense-pack method, you are only filling the joist spaces, and that leaves massive amounts of uninsulated space above the drywall and between the beams that the blower can't reach. If you're trying to keep the cold air out, simply stuffing the joists isn't the whole plan. You're going to need to account for those open top sections as well.

You definatly need to think about air sealing before you blow anything in there. If you don're just filling the joists, you'll still have massive heat loss around the perimeter of the cavity. I did a similar job once where we found the main source of leaks wasn't the hole, but the gaps around the 2x8 top plates wich were open by nearly half an inch all the way around. Make sure that perimeter is taped and sealed first to get the biggest improvement.

Then you can proceed with filling the joists from below.

Update: went ahead and had a crew dense-pack it through the light hole, and both rooms alredy feel way better. That said, there's still a draft along the outside wall that didn't go away. The air sealing point in the replies got me thinking I shold have done that first. Is it still possable to seal the top plates now that the cavities are full, or would I have to pull the insulation back out of the way?

Join the Discussion

Have something to add? Share your thoughts — no account required.