I know this is a topic often covered on uk.d-i-y, but I can't see an answer to the specifics of what I want do:
As it is now: Old chapel I'm converting to a home. Incomer on overhead wires. TN-C-S (PME) Earthing Old rewirable fuses CU The only wiring from the CU is a double socket within 30cm of it, no other domestic wiring whatsoever.
What I want: Meter moved to a new location, but a simple one that involves shortening the incomer by about 1.5m and actualling just moving it horizonatlly on the same wall. (and ideally the meter upgraded at the same time, it's a white meter (off-peak) with a mechanical time clock next to it, and a 60A fuse.)
A new split-load CU. (Currently there are two rewirables,and a third MCB unit (connected to the timeclock) that used to be hooked to night storage heaters).
For now - exactly the same as before, just a double socket next to the new CU.
Now I've kicked off the process of having the meter moved - and they do make it complicated - one lot of boys to shorten the cable and fit the supply fuse - another lot to connect the new meter. The current price estimate is =A3350, outrageous, but I shall work on getting this down (however the meter move is unavoidable so I shall have to pay whatever they charge).
If this was pre January 2005, I would just screw a new CU to the wall, wire in a double socket and connect meter tails ready for the changeover. However they need to see a test certiciate before work can proceed.
Q1 - Is there a way I can satify this requirement without getting somebody Part P qualified in to do the work? (BTW I'm MIEE, CEng, PhD Elec Eng - but that carries no weight these days - though realistically my professional experience in electrical power systems was all medical x-ray equipment, not domestic wiring regulations).
There are 2 rising water mains into the building. One is disused and within 2m of the CU. The other about 7 away. Both currently have earth bonds - and since demolition of old stud walls they are just strung along the wall.
The disused main is no problem, the best route to the other would be to run the bond wire under the timber floor of the ground floor, bring it above ground with the pipe and clamp there.
Q2 - Is it permissable to have an Earth bond wire that is not clipped into place and in contact with the ground under a timber floor? Getting in there to clip it into place would be "difficult".
Q3 - Who provides the earthing mecca? Currently it's a block screwed down next to the meter. Is it acceptable to do that entirely inside the CU and leave a single "earthing tail" for them to connect to the combined neutral/earth?
Q4 - what is the current requirement for testing of earth bonds to water pipes?
Obviously Q2,Q3 & Q4 are a bit academic if the answer to Q1 is "You must contract someone Part P qualified to do the whole lot".