Thanks for the many good tips. Hired a self powered concrete breaker found using the Stihl saw did not speed the job up but good for getting a straight edge. The first 4 square feet took two hours most of that trying to remove a very heavy breaker impaled right through the concrete-luckily it was not reinforced. Speeded up tremendously after learning to take little bites at a time and broke out 8 foot by 4 foot section in 6 hours with tea breaks. Concrete breaker hire was £42 for a day or £100 for a week.Just got it for the week as I have a 450mm inspection pit to insert in the pad and a drain to break out.