I'm installing 1 3/4 t&g osb for a basment floor on 2x4 sleepers. This is my first subfloor project.
How do I get the tongue of one 4x8 sheet to mesh with the groove in the adjoining one? Pushing doesn't seem to do it (although I found out that construction glue is really, really sticky), and hammering just smashes the hammered side. Kicking it didn't work.
I'm wishing for something like a come-along that would PULL the two sheets together, but I have no idea if such a thing exists.
I'm doing this myself, so I'm wondering if the normal method is to have several beefy guys just lean into each sheet to make it snap in. If so, the damn book neglected to mention that in the "needed tools" list!
Maybe use a hydraulic jack to push, & a 6' 2x4 along the edge?