Hi,
My kitchen refurb continues slowly. I have finished plastering and will post about that soon.
I ripped out all the old pipe work when I started so rightly or wrongly, now have to re plumb the dishwasher. If you remember I was asking about using solvent weld pipe.
I read the wiki:
and there is a paragraph about halfway down that says "New pipe work should have a fall of 18-90 mm/metre to comply with building dregs part H. Pipe work outside these figures has increased tendency to deposit solids, increasing risk of blockage. "
The range 18mm to 90mm is a big one; is it better to be nearer 18mm or
90mm fall per metre? Why aren't the regs more specific!?I am unsure how to achieve these levels of fall. Fittings will only accept pipes at one angle. I thought they were at 92 degrees? Perhaps there is a slight margin in push fit and compression fittings but even so the wriggle room will not be that generous. How would you fit a pipe falling 90mm/m into a tee?
It doesn't help that the drain in my kitchen is offset, halfway between the sink and the dishwasher, so my plan was to use a tee to split it to the dishwasher on the one side and the sink on the other side. It is only 40mm but to upgrade it would involve digging down through a concrete floor, so if it's not broke, I figure don't fix it. I haven't had problems before with sink and dishwasher draining at the same time.
Can I also tee the boiler condensate drain into the same pipework or do I risk siphoning the trap in the boiler every time I empty the sink?
TIA