Hi,
I live in a late georgian/early victorian townhouse. The basement is currently 218 cm from concrete floor to exposed ceiling joist. We are moving our kitchen into the basement, and planning to fit some underfloor heating and insulating boards. I'm quite tall and want to keep the ceiling height as high as possible.
The builder has dug a trench for a drain, and we've found that the concrete floor is approx 10cm deep, then turns into brick below that, Other than the work itself, would there be any problem in removing the concrete layer completely, then re-laying the boards and tiles onto a much thinner layer of concrete or screed? I'm assuming that if the brick was the original floor layer, then this is unlikely to cause structural problems. If we did do this, should we do anything to make sure we don't get damp coming up?
Thanks,
Miles