Just sorting out the calculations for the rewire now that the Part P route is agreed with building control, and have come across a problem(?) with specifiying the CU. Basically given that I'm not supposed to allow for diversity at the CU I can't wire the house on a single consumer unit. Any electrical installation experts advice on reasonable cost solution very welcome. The reality is that I'm never going to exceed the 100A supply as no electric showers and immersion heater is emergency only if the boiler (in fact both boilers) breaks down (pretty unlikely) and no electric heating apart from comfort undertile heating in the cellar.
I want to wire the house in 4 'zones' with the following circuits:
Zone 1 = 2nd floor - 1x socket ring (32A) + 1x lighting (6A) Zone 1 = 38A total
Zone 2 = 1st floor - 1xsocket ring (32A) + 1x lighting (6A) + central heating control (6A) + immersion (13A) Zone 2 = 57A total
Zone 3 = Ground floor RHS - 1x socket ring (32A) + 1x lighting (6A) Zone 3 = 38A total
Zone 4 = Ground floor LHS - 1x socket ring (32A) + 1x socket radial (20A) + lighting (6A) + range cooker (32A) + refridgeration circuit (6A) Zone 4 = 96A total
Zone 5 = Basement - 1x socket ring (32A) + 1x lighting (6A) + kiln (16A) + tile heater (13A) + smoke alarms (6A) Zone 5 = 71A total
Nominal Installation Total = 300A
Clearly this is ridiculous given that the total number of circuits is
18 the realistic diversity is very high. The only way I can see to get the nominal total down is by combining circuits but this still won't get me all the way as the house is 270sqm so I need at least 3 ring circuits.My original plan was to use an MK sentry CU with 21 ways (19 usable) and use separate RCBOs for the socket circuits to avoid the risk of nusiance trips from earth leakage on electronic kit (PCs etc.). This would have the required number of ways and is in reality adequate for my needs.
To meet the supposed design requirements I would need to use 3 CUs fed from a Henley block which I can do but this seems like overkill. The cost difference isn't huge it's just the hassle factor and having to run meter tails over longer distances to the 3 dis boards.
Any advice on what is reasonable/acceptable in practice.
Sorry the post is so long but it's a big installation!
Fash
Zone 5