Hi all,
Yesterday I laid some concrete as part of my drive, but other than not using it for a while I'm not sure 1) how long to leave it before use and 2) when I can remove the shuttering.
As I now feel rather stupid, could someone advise. BTW the concrete is approx. 100 - 120mm thick
TIA
--
--dave

snipped-for-privacy@nospam.org.uk
  Click to see the full signature.
Add pictures here
<% if( /^image/.test(type) ){ %>
<% } %>
<%-name%>
Add image file
Upload
Dave wrote:

Before parking on it? 3-4 days, pref. a week.

Now is fine.
--
Grunff


Add pictures here
<% if( /^image/.test(type) ){ %>
<% } %>
<%-name%>
Add image file
Upload
Hello Dave

In this weather? 1 day for foot. 3 days for a light car. Over a week for anything heavier.
Remove shuttering when the concrete will stay put without it. By now, certainly.
--
Simon Avery, Dartmoor, UK
uk.d-i-y FAQ: http://www.diyfaq.org.uk /
  Click to see the full signature.
Add pictures here
<% if( /^image/.test(type) ){ %>
<% } %>
<%-name%>
Add image file
Upload

Foot traffic 24 Hrs. Cars - after 3 days .... but keep soaking the drive with water, the more water the sooner it will harden (concrete sets by chemical reaction - not by drying out)
Rick
Add pictures here
<% if( /^image/.test(type) ){ %>
<% } %>
<%-name%>
Add image file
Upload

Thanks for the replies gentlemen:)
--
--dave

snipped-for-privacy@nospam.org.uk
  Click to see the full signature.
Add pictures here
<% if( /^image/.test(type) ){ %>
<% } %>
<%-name%>
Add image file
Upload

HomeOwnersHub.com is a website for homeowners and building and maintenance pros. It is not affiliated with any of the manufacturers or service providers discussed here. All logos and trade names are the property of their respective owners.