I hired a contractor to remodel a 1/2 bath into a full bath. The original contract was signed in mid may with no date of completion stated...but contractor said "two weeks".
In mid June, the project was still not even close to being completed, so we re-wrote the contract with a final completion deadline with monetary penalties if said dealine wasnt met. Both partied signed the written contract that also stated that ZERO money was due until the porject was 100% completed.
Now, the contractor is demanding that I pay him 80% of the cost even though the project is *still* not even close to completion (in mid august).
I guess what im asking is: How legal is a signed contract that wasnt drafted by a lawyer? According to the contract, I dont owe him a penny....but he has purchased some materials that are in my house and installed.
Any advice would be great.
thanks, pat