Cure time on a pad

Poring a pad for a double wide home compact gavel rebar on a two foot grid pattern what is the minimum time after the pad is poured till I can safely set double wide
Add pictures here
<% if( /^image/.test(type) ){ %>
<% } %>
<%-name%>
Add image file
Upload
On Thu, 13 Oct 2016 14:44:01 +0000, Larry Herman

At least a week. You will be at well over 90% in a month. Keep it wet.
Add pictures here
<% if( /^image/.test(type) ){ %>
<% } %>
<%-name%>
Add image file
Upload
Larry,
The mixture, thickness, and temperature are important. At a guess, your pad will reach 70% strength in about 7 days.
Dave M.